OVERVIEW 
JURISDICTION (including UP & DN line)
| Gauge | Section | Route km | BG | Chagsari to Agthori to Furkating (excluding) | 333.94 | Azara (excluding) - Kamakhya | 3.58 | Kamakhya - Jagiroad (UP line) | 63.7 | Dharamtul – Lumding (UP line) | 104.740 | Chaparmukh – Senchoa | 20.26 | Senchoa – Silghat | 61.18 | Senchoa - Mairabari | 48.98 | Patharkhola – Mandardisa (Bye Pass) | 8.000 | Lumding - Badarpur | 169.24 | Badarpur - Silchar | 29.55 | Badarpur – Karimganj | 20.20 | Karimganj - Baraigram | 21.55 | Baraigram - Agartala | 181.87 | Arunachal – Jiribam | 49.81 | Katakhal - Bhairabi | 83.55 | Karimganj – Maissashan | 10.57 | New Karimganj – By Pass Cabin | 1.40 | Agartala – Sabroom | 114.660 | Baraigram - Dullabchera | 28.97 | Jiribam - Vangaichungpao | 11.21 | Tetelia – Kamalajari | 9.74 | DISTRICTS SERVED
State | District | Assam | Kamrup, Kamrup Metro, Morigaon, Nagaon, Hojai, Karbi Anglong, Golaghat, Dima Hasao, Cachar, Hailakandi & Karimganj | Nagaland | Dimapur. Kohima, Mokokchung & Wokha | Tripura | North Tripura, Dhalain, Unukoti, Gomoti & West Tripura | Manipur | Churachandpur, Bishnupur, Senapati & Imphal West | Mizoram | Kolasib, Aizwal & Lunglei | Meghalaya | East Khasi, West Jaintia Hills and Ri-Bhoi | ROUTE KILOMETERS
ROUTE | ROUTE KM | TRACK KM | D | 333.94 | 677.008 | E | 874.32 | 1016.45 | Total | 1208.26 | 1693.45 | Under Construction (New line project) | 448.60 | | Dhansiri-Zubza- Thizama | 123.14 | Vangaichungpao-Imphal | 112.57 | Bhairabi-Sairang | 50.50 | Kamalajari-Byrnihat | 10.91 | Byrnihat-New Shillong | 105.30 | Agartala-Akhaura | 13.00 | Grand Total | 1656.86 | 1693.45 | Following Doubling projects are in different stages of execution by Construction Organization: Section | KM | Jagi Raod- Dharamtul Doubling | 18.75 | Total | 18.75 | SECTION SANCTIONED FOR RAILWAY ELECTRIFICATION WORKS:
Sl | Section | RKM (to be electrified) | RKM (electrified) | Executing agency | Current status/TDC | 1. | AGT-GHY | 13.5 KM | 13.5 KM | RVNL | CRS completed. | 2. | GHY(Excl.)-LMG(Incl.) | 181 KM | ---- | CORE | Tentative CRS of 60 KM (GHY-JID) on 20/02/22 | 3. | CPK(Excl.)-SCE-SHTT-MBO | 129 KM | --- | CORE | Tentative CRS 31/03/2022. | 4. | Package-6 LMG(Excl.)-FKG(Excl.) | 137.19 KM | --- | IRCON | Tender opened on 04/02/22, under evaluation stage. | 5. | LMG(Excl.)-BPB(Incl.) | 171 KM | --- | RITES | Tender opened, under evaluation stage. | 6. | Package-2 BPB(Excl.)-SCL-JRBM- BHRB-KXJ-MSSN-DMR-AGTL-AHAURA- SABROOM | 557.865 KM | --- | IRCON | Work awarded to L&T. | CATEGORY OF STATION BREAKUP NSG-2 | NSG-3 | NSG-4 | NSG-5 | NSG-6 | HG-2 | HG-3 | Total | 1 | 2 | 2 | 11 | 111 | 4 | 34 | 165 | Welfare Facilities: | Nos | Locations | Railway Hospitals | 02 | LMG & BPB | Health Units | 13 | JID, CPK, HJI, LMG, DMV, NHLG, MBG,NHGJ, SCL, KXJ, DMR, GHY, NGC | Railway Schools | 03 | LMG, DMV & BPB | ACCIDENT PREPAREDNESS EQUIPMENTS | TYPE | LOCATIONS | | 140 T Crane | NGC , BPB & LMG | ARME | Scale-I | GHY, LMG & BPB | Scale-II | CPK, DMV, SCL, NHLG, DMR & KXJ | ART | Scale-A | NGC, LMG & BPB | REVENUE PERFORMANCE OF LUMDING DIVISIONUPTO THE MONTH OF JUNE (F.Y.2023-24). (Amount in Crore) ITEM | TARGET 2021-22 | Achievement 2021-22 | TARGET 2022-23 | Achievement 2022-23 | Target 2023-24 | Prop. Target up to the month of JUNE/23 | ORIGINATING BASIS | ACTUAL (22-23) JUNE/22 | ACTUAL (23-24) JUNE/23 | VAR w. r. t LAST YEAR | VAR w. r. t TARGET | Passenger Revenue | 659.96 | 467.35 | 510 | 705.96 | 735.05 | 183.75 | 150.49 | 199.33 | +32.45% | +08.48% | Other coaching Revenue | 109.52 | 100.18 | 120 | 157.15 | 172.40 | 43.11 | 24.27 | 47.86 | +97.20% | +11.02% | Goods Revenue | 291.45 | 190.06 | 220 | 307.36 | 339.91 | 84.99 | 63.78 | 57.33 | -10.11% | -32.55% | Sundry Revenue | 76.42 | Comml) 4.09 | 4 | Comml) 8.91 | 76.76 | 19.20 | Comml.) 1.01 | Comml.) 4.88 | | Engg) 58.44 | 80 | Engg) 28.47 | Engg.) 5.39 | Engg.) 15.39 | T)62.53 | 84 | T)34.54 | Total) 6.40 | Total) 20.27 | +216.72% | +05.57% | Total | 1137.35 | 820.12 | 934 | 1207.86 | 1324.12 | 331.05 | 244.94 | 324.79 | +32.60% | -1.89% |
|
|
|
|
|
|
|
|
|
|
|
| PASSENGER (Passenger in Million) ITEM | TARGET 2021-22 | Achievement 2021-22 | TARGET 2022-23 | Achievement 2022-23 | Target 2023-24 | Prop. Target up to the month of JUNE’23 | ACHIEVEMENT | % VARIATION | 2022-23 JUNE/22 | 2023-24 JUNE/23 | VAR w. r. t LAST YEAR | VAR w. r. t TARGET | No of Passenger Booked | 13 | 14.25 | 24.06 | 25.08 | 30 | 7.50 | 5.35 | 7.34 | +37.20% | -2.13% | PARCEL REVENUE (Amount in Crore) ITEM | TARGET 2021-22 | Achievement 2021-22 | TARGET 2022-23 | Achievement 2022-23 | TARGET 2023-24 | Prop. Target up to the month of JUNE’23 | ACHIEVEMENT | %VARIATION | 2022-23 JUNE/22 | 2023-24 JUNE/23 | VAR w. r. t LAST YEAR | VAR w. r. t TARGET | Parcel Revenue | 35.09 | 21.58 | 35 | 47.86 | 55 | 13.74 | 5.71 | 14.31 | +150.61% | +4.15% |